Title Standardization of Factors Classification Associated with Cost and Schedule Variations in Road Construction Projects
Authors 문준부(Mun, Junbu) ; 이주희(Lee, Juhui) ; 백승원(Baek, Seungwon) ; 이강욱(Lee, Kangwook) ; 윤성민(Yun, Sungmin)
DOI https://doi.org/10.12652/Ksce.2023.43.6.0821
Page pp.821-830
ISSN 10156348
Keywords 공사비·공사기간 증감요인; 도로건설공사; 표준화 Cost and schedule variation factors; Road construction project; Standardization
Abstract Various studies has tried to unveil causes of cost overrun and schedule delay in the road construction project. However, these causes need standardization due to difference by guidelines, relevant research, and facilities. Therefore, this study identifies and elaborate standard road construction cost and schedule variation factors that can be used in the planning and execution of the project. variation factors have been derived and grouped through literature review and modified and supplemented through expert interview. In addition, the connection with the relevant guidance factors is confirmed and the usability is reviewed by applying actual road construction cases. The factors suggested in this study comprehensively include factors of related guidelines and previous research, more clearly distinguish, support decision making.