Mobile QR Code QR CODE : Journal of the Korean Society of Civil Engineers
Title A Study on Advance Rate under the Operating Conditions of EPB Shield TBM Based on TBM Operation Data
Authors 안만선 ; 임광수 ; 김경주
Page pp.839-848
ISSN 10156348
Keywords TBM;EPB Shield;net advance rate;total thrust force;cutter head RPM;터널보링머신;토압식 쉴드;순굴진속도;총추력;커터헤드 회전속도
Abstract TBM (Tunnel Boring Machine) tunnel should be carry out with the adopted machine until the end of excavation because of impossibility of replacement or modification of machine. Observation of the face of the tunnel is difficult, especially in EPB(Earth Pressure Balance) shield TBM, predict changes in the ground condition with analyzing data, collected during the excavation, and it should be reflected in construction. Until recently, subjects of studies on TBM are mainly the determination of machine and the development of advance rate prediction model, according to the characteristics of ground which is the target of excavation. However, study focused on the estimation of ground conditions and the improvement in operational methods using excavation data of TBM equipment, the principal of the excavation, has been done not so much. This study examine the variances in advance rate depending on changes in operating conditions and evaluate the optimal operating conditions of adopt machine, using working data obtained from EPB shield TBM project. The result of this study is suggested as follows. First, cutter head RPM and total thrust force are biggest influences on advance rate, Second, it is recommended for proper advance rate that total thrust force is controlled while optimum cutter head RPM is kept, Third, according to the increasing trend of total thrust force, the changes in ground conditions can be predicted, the appropriate operating conditions can be determined.