Mobile QR Code QR CODE : Journal of the Korean Society of Civil Engineers
Title Productivity Analysis on the Standard Quantity-Per-Unit Costing Method and Work Crew Combination Method : Focused on Non-Vibration Mass Excavation Method
Authors 이동욱 ; 조홍준 ; 이근조 ; 김남식
Page pp.457-468
ISSN 10156348
Keywords standard estimating;historical cost data estimating;standard quantity-per-unit costing method;work crew;표준품셈;실적공사비;원가계산적산방식;작업조
Abstract Recently, the non-vibration mass excavation method is used on sewage pipes and road construction sites in Jeju. However, a construction cost estimation based on the unit quantity does not provide a proper unit price. In this study, a comparison of the productivity of the standard quantity-per-unit costing method and the one of the work crew combination method was made based on the site monitoring of the non-vibration mass excavation method that is used in construction sites near Jeju. For this, data of 35 sites were collected: a regression equation was derived from the 30 data, and verification was carried out through the remaining 5 data. The analysis concluded that a day’s workload is 16.43㎥. In addition, a combination of the equipment considering the site conditions and the amount of labor, which varies with the number of work crew was obtained in order to estimate the construction cost of the work crew combination method. The construction cost was calculated based on the one-day workload (16.43m3) derived from the regression analysis. The cost then was analyzed and compared with the standard quantity-per-unit costing method.